Welcome to the  Spillway page of the

FSMR website

THIS PAGE LAST UPDATED 04-01-09

 This page  shows the construction in 2007of the new lake outfall spillway.

The bridge required heavy maintenance and so it was decided to improve its construction during this process creating a safer more aesthetic construction and refurbish, or replace the supporting RSJ,s at the same time. Also new blue brick support walls were added

 

The blue brick edgings are being added to improve bridge stability and water erosion protection of the footings from the lake outflow here during winter rains.

 

During a barmy mid April weekend in 2007 with little rain, our resident brickie, FSMR member Kev takes a break from the station construction work to lay the new blue brick walling

The guy standing overseeing the job is our treasurer ensuring the project stays on budget!!

 

 

 

 

The track panels and steel plate decking were removed exposing the RSJ support beams. These were found to have corroded to the point where it was deemed necessary to renew them. They were removed the following weekend and new RSJ’s were installed over the May BH

Note the flood gauge on the lake edge that goes to 4 feet above high water!!.

Although never that high, the lake has breached the track walls along the track in previous wet winters

 

 

 

While in the workshop over the winter 2006 / 2007, the new trusses were fabricated

New spillway bridge being fabricated in the FSMR workshops at Stapleford

 

 

The new side trusses awaiting painting and cross bracing

 

 

The new side trusses are painted, and ready for transport down to the lakeside to be installed on the bridge

 

The new blue brick side walls are installed, and the centre support islands are being constructed out of concrete, brought to the site by train

 

 

 

The new side trusses painted, and transported down to the lakeside to be installed on the bridge

 

The new bridge minus decking

 

 

The new bridge receives its decking plates

 

Almost complete, the new bridge just requires the approaches to be concreted and ballasted and centre plates to be added

As can be seen, the new bridge also offers a much safer access for pedestrians around the railway during non-running periods on the railway

 

 

And of course, the last item to fit, the obligatory builders plate!!

 

 

Taken on a very cold Easter Sunday in March 2008

The Jubilee 5565 poses on the new structure.

 The previous week, flood water was almost up to the retaining wall as it roared over the outfall

 

 

 

 

 

Taken under much warmer conditions over the first May BH weekend 2008 a 751 “John H Gretton” runs over the new bridge

 

 

 

And some you tube footage of a drivers eye view of the bridge taken on a very cold new years day 2009 as the green John H Gretton trundles along lakeside

 

BACK TO PROJECTS PAGE

 

BACK TO MAIN PAGE