Welcome to the Projects and developments page of the FSMR website

This page was last updated 30-08-2010

 

 

The FSMR members undertake a variety of projects on the railway.

None compare to the task in the early days back in 1995 of rebuilding the tunnel, but all can be challenging as well as interesting. A "project manager" usually takes charge, and members can just turn up and help on what suits them best, be it track, electrical, civil, or locomotive engineering. The FSMR have a selection of dumper trucks, and access to the farm estates JCB. And with mining engineers, architects, electrical and mechanical engineers as members, no task is too large in the preservation world!!!!

 

Just to put in perspective what massive engineering challenge we constantly face against nature on the railway here are some  pictures taken during March 2007 of the railway under water

 

Below along the back straight in the distance is the normally “dry” culvert overspill bridge, the actual small stream is piped under the track bed some 6 feet below and only flows under the culvert overflow at times of heavy rain

 

 

 

Below is “Coleby’s” culvert bridge, the stream runs through a  24 “ pipe, some 6 feet  under the railway to the bottom left joining the main river Eye behind the bridge

 

 

 

 

Below is the second crossing, Jenny’s bridge under a torrent of water, the normal river level runs some 7 feet below the deck height!! And is normal 6 feet deep at this point!! So the water is over 13 feet deep

Note the large tree trunk wedged against the bridge.

 A constant danger which required the use of the farm tractor to remove

 

 Grass cutting

 Grass cutting prior to the August BH

Another cut will be needed prior to the winter

 

Civils

During winter and spring 2006/2007, we  undertook a major rebuild of the lakeside outfall spillway bridge. This had been identified as requiring major maintenance and so it has been decided to update the design at the same time. Abutments were renewed and a complete new wider and stronger steel superstructure was fabricated in our workshops and assembled at the lakeside. Work was completed prior to the 2007 summer events

There is a page created showing this work click here to view

Spillway

 

Below is the new lake outfall spillway bridge in place March 2008

 

 

 

There was also a project over  4 years which was officially completed and opened on 12th October 2008 to re-develop the whole terminus platform and station area to provide better catering and seating facilities and re roof the platform canopy as the old corrugated roofing is badly corroded at the edges. Architect plans were drawn and passed by the council planning.  Foundation construction was completed in 2006 by local building contractor, and handed over to the FSMR team (led by a member who is a skilled builder). The building was completed prior to opening in October 2008 although there was some internal fitting out completed for June 2009 when the station saw its first public passengers, but it had already been used as a refreshment room with the log stove fire put to good use cooking jacket potatoes! For the bonfire night event and during the Easter 2009 private running

The new station building being based on the Midland Railway Settle and Carlisle stations design.

Follow the link to the new station page

 

station in Feb 2008 with roof joists being completed

 

Some work was also completed in spring 2010 on the platforms to replace sections of frost blown concrete, in preparation for the summer openings.

 

Track

Ongoing re-sleepering of track continues, the original 1970's jarah sleepers showing their age, especially on the extension. Go to the picture gallery for pictures of the re-sleepering methods.

We have started the process of lifting complete panels and digging out the bed with the FSMR tractor loader. The bed then receives a geo-tex membrane before new ballast is added and the panel is  replaced on new sleepers. The record is 3 panels  completed in one day. The oldest sections are being tackled first through the woods. We are also took the opportunity this spring to install an access crossing at badgers curve to allow heavy machinery access without damage to the track  e.g tractor mower and JCB .At the same time, 9 panels of original track were renewed through the wooded section.

 

Another record in autumn 2006 with 4 panels !! replaced over the weekend of 14th 15th October 2006 in the same area back to badgers bend completing this area. We also added a new sleeper retaining walls to the bank to prevent soil erosion contamination of the ballast.

And all this with the Berkshire providing the exotic motive power for the day in the diesels absence

Follow this link for detailed pages and pictures of the October 2006 track work

 

 below is the work completed looking, towards badgers bend, on bonfire weekend with the Berkshire providing the works train motive power in the diesels absence

 

 

 

Yet another record in Feb 2008 with 6 panels !! being replaced over the Saturday 16th on Chestnuts curve

Follow this link for detailed pages and pictures of the Feb and March 2008 track work

 

 See also the picture gallery for pictures of some more track work 

 

Locomotives

-5565 LMS Jubilee

This was failed on inspection of the boiler during the June 2009 event and will require a new boiler and or firebox designing and constructing and thus is out of action till probably 2012.

 The boiler has been removed from the frames for detailed analysis of the options available.

 In the Jubilees absence, the Curwen Atlantic and GWR Saint were paired up over the June and August BH weekends  and it is envisaged the same thing will be done at the two events in 2011 with the new 31 class loco keeping the operational numbers at 5 the minimum needed for running the intensive service. The Curwen is quite able to handle 9 coaches on its own but the Saint could not. so this is the best way to be able to have the Saint in operation.

751 John H Gretton had an extensive boiler off overhaul with work on the tubes and mechanicals over winter 2009 2010 and ran over the 2010 weekends and will be in use for private running over the autumn and winter

752 Berkshire was in use over June and August 2010 and may well be in use over the Winter on private running

 

 

 

 

 

 

Some FSMR members are also constructing their own 1/5th scale 10 1/4" gauge diesel or steam locos, these currently are:

 

 

Great Central Railway 11F Improved Director 505 'Ypres'


 
Work on the design started Mid 2005
Progress to date. Nov 2008-11-03

Tender completed
Frames, stretchers, footplates, splashers, valences, smokebox made. All cast parts cast. Cylinders, covers, valve chest all part machined and awaiting boring. Boiler design complete. Front bogie complete. Connecting and coupling rods part machined awaiting boring. Crank axle made awaiting assembly. Axle boxes and horns machined awaiting boring.  
 
Length over buffers 3600mm
Height to chimney top 835mm
Width 540mm
Boiler 160 psi (superheated)
Cyclinders (2) 89 x 140mm
Piston valve inside Stephensons
Driving wheel 420mm dia

 

 

 

Replica of 1899 Midland railway Johnson 4-2-2 "Spinner"

The tender is built, and work progresses on the rest, no arrival date at Stapleford yet!

 

Brush Class 60 D/E 

Fully working Diesel Electric replica featuring latest design in traction motors driven off a diesel alternator, just like the real thing!!

Date for arrival and commissioning 2011 or 2012 Who knows, by which time with the national fleet now down to a hand full, it will probably be a heritage diesel like the warship!!

 

 

 

  

BACK TO MAIN PAGE