Welcome
to the Projects and developments page of the FSMR website
This page was last updated 26-12-2011

The FSMR members undertake a variety of projects on
the railway.
None compare to the task in the early days back
in 1995 of rebuilding the tunnel, but all can be challenging as well as
interesting. A "project manager" usually takes charge, and members
can just turn up and help on what suits them best, be it track, electrical,
civil, or locomotive engineering. The FSMR have a selection of dumper
trucks, and access to the farm estates JCB. And with mining engineers,
architects, electrical and mechanical engineers as members, no task is too
large in the preservation world!!!!
Just
to put in perspective what massive engineering challenge we constantly face
against nature on the railway
Take a
look at this new page showing he railway under water
Follow
this link for detailed pages and pictures of flooding
Grass cutting
Grass
cutting is complete
for this year
Civils ![]()
During winter and spring 2006/2007, we
undertook a major rebuild of the lakeside outfall spillway bridge. This had been
identified as requiring major maintenance and so it has been decided to update
the design at the same time. Abutments were renewed and a complete new wider
and stronger steel superstructure was fabricated in our workshops and assembled
at the lakeside. Work was completed prior to the 2007 summer events
There is a page created showing this work
click here to view
Below
is the new lake outfall spillway bridge in place March 2008

There was also a project over 4 years which was officially completed and
opened on 12th October 2008 to re-develop the whole terminus
platform and station area to provide better catering and seating facilities and
re roof the platform canopy as the old corrugated roofing is badly corroded at
the edges. Architect plans were drawn and passed by the council planning. Foundation construction was completed in 2006
by local building contractor, and handed over to the FSMR team (led by a member
who is a skilled builder). The building was completed prior to opening in
October 2008 although there was some internal fitting out completed for June
2009 when the station saw its first public passengers, but it had already been
used as a refreshment room with the log stove fire put to good use cooking
jacket potatoes! For the bonfire night events and during the Easter private runnings.
It has subsequently been a godsend for public running events acting as the
railways refreshment and souvenir shop
The
new station building being based on the Midland Railway Settle and
Follow
the link to the new station page
Some work was also completed in spring 2010
on the platforms to replace sections of frost blown concrete, in preparation for
the summer openings.
Track 
Ongoing re-sleepering of track
continues, the original 1970's jarah sleepers showing
their age, especially on the extension. Go to the picture gallery for pictures
of the re-sleepering methods.
We have started the process of lifting
complete panels and digging out the bed with the FSMR tractor loader. The bed
then receives a geo-tex membrane before new ballast
is added and the panel is replaced on
new sleepers. The record is 3 panels
completed in one day. The oldest sections are being tackled first
through the woods. We are also took the opportunity this spring to install an
access crossing at badgers curve to allow heavy machinery access without damage
to the track e.g
tractor mower and JCB .At the same time, 9 panels of original track were
renewed through the wooded section.
Another record in autumn 2006 with 4 panels
!! replaced over the weekend of 14th
And all this with the
Follow
this link for detailed pages and pictures of the October 2006 track work
below is the work completed looking, towards
badgers bend, on bonfire weekend with the

Yet
another record in Feb 2008 with 6 panels !! being replaced over the Saturday
16th on Chestnuts curve
Follow
this link for detailed pages and pictures of the Feb and March 2008 track work
See also the picture gallery for pictures of some more track work
We now have a dedicated person in charge of Pway work who co-ordinates any major renewal and ongoing sleeper replacement, with organised work parties on large jobs which is all logged on a database as per full size!!
Locomotives ![]()
-5565
This was failed on inspection of the
boiler during the June 2009 event and will require major work on the boiler and
firebox and thus is out of action till 2013 at least
The
boiler has been removed from the frames for detailed analysis of the options
available.
In
the Jubilees absence, the Curwen Atlantic and GWR Saint were paired up over the
June and August BH weekends and the same
thing will be done at the two events in 2012 with the new 31 class loco keeping
the operational numbers at 4 the minimum needed for running the intensive
service. The Curwen is quite able to handle 9 coaches on its own but the Saint
could not. so this is the best way to be able to have
the Saint in operation. However due to failure of the NKP Berksire,
it may be that the Saint is paired with the warship diesel to release the
Atlantic
751 John H Gretton
was overhauled over winter and Spring
2011 and ran during the summer and will be
available for New year 2012 and Easter
private running
752 Berkshire was failed on the Sunday
night of the BH running due to stay leak and was scheduled to be withdrawn in
any case for its 10 year major boiler ticket. Boiler has been removed and it
has been decided to replace the whole firebox at an external contractor. Follow
here or on Twitter for updates on this work
However this means it is unlikely to
feature in our 2012 public events
The private Niagara and

Some FSMR members are also
constructing their own 1/5th scale 10 1/4" gauge diesel or steam locos,
these currently are:
Great
Central Railway 11F Improved Director 505 '
Work on the design started Mid 2005
Progress to date. Nov 2008-11-03
Tender completed
Frames, stretchers, footplates, splashers,
valences, smokebox made. All cast parts cast.
Cylinders, covers, valve chest all part machined and awaiting boring. Boiler design complete. Front bogie complete. Connecting and
coupling rods part machined awaiting boring. Crank
axle made awaiting assembly. Axle boxes and horns machined awaiting boring.
Length over buffers 3600mm
Height to chimney top 835mm
Width 540mm
Boiler 160 psi (superheated)
Cyclinders (2) 89 x 140mm
Piston valve inside Stephensons
Driving wheel 420mm dia

And the loco construction progresses as shown
November 2011 when the boiler shell was dropped on the frames to check the fit

Replica of 1899
The tender is built, and work progresses on
the rest, no arrival date at Stapleford yet!
Brush
Class 60 D/E
Fully working Diesel Electric replica
featuring latest design in traction motors with 6 driven off a diesel
alternator, just like the real thing!!
Under construction since the late 90s by a partnership including our
chairman who happens to be a Brush (now Wabtec) electrical engineer, and was
involved with commissioning the new class 60 fleet and still is involved
maintaining the survivors
Date for arrival and commissioning 2012? Who knows, by which time with the national
fleet now down to a hand full, it will probably be a heritage diesel like the
warship!!
Update
Nov 2011 Currently on static loading tests in the owners garden shed!!
The neighbours must love him

