Welcome to the Projects and developments page of the FSMR website

This page was last updated 05-05-2008

 

 

The FSMR members undertake a variety of projects on the railway.

None compare to the task in the early days back in 1995 of rebuilding the tunnel, but all can be challenging as well as interesting. A "project manager" usually takes charge, and members can just turn up and help on what suits them best, be it track, electrical, civil, or locomotive engineering. The FSMR have a selection of dumper trucks, and access to the farm estates JCB. And with mining engineers, architects, electrical and mechanical engineers as members, no task is too large in the preservation world!!!!

 

Just to put in perspective what massive engineering challenge we constantly face against nature on the railway here are some  pictures taken during March 2007 of the railway under water

 

Below the back straight is swamped, it is hard to believe that the river normally flows

 Over 10 feet below rail height along to the right

 

 

Below further along the back straight in the distance is the normally “dry” culvert overspill bridge, the actual small stream is piped under the track bed some 6 feet below and only flows under the culvert overflow at times of heavy rain

 

 

 

Below is “Coleby’s” culvert bridge, the stream runs through a  24 “ pipe under the railway to the bottom left joining the main river Eye behind the bridge

 

 

 

Below is the first river crossing, Haven bridge, which is normally the highest crossing point above the river, the bottom of the support beam sitting over 8 feet above normal water level!!

 

 

 

Below is the second crossing, Jenny’s bridge under a torrent of water, the normal river level runs some 7 feet below the deck height!! And is normal 6 feet deep at this point!! So the water is over 13 feet deep

Note the large tree trunk wedged against the bridge.

 A constant danger which l required the use of the farm tractor to remove

 

 Grass cutting

 The first seasons weed-killing  train will run in mid April as the cold weather has delayed growth.

Civils

During winter and spring 2006/2007, we are also undertook a major rebuild of the lakeside outfall spillway bridge. This had been identified as requiring major maintenance and so it has been decided to update the design at the same time. Abutments were renewed and a complete new wider and stronger steel superstructure was fabricated in our workshops and assembled at the lakeside. Work was completed prior to the 2007 summer events

There is a page created showing this work click here to view

Spillway

 

Below is the new lake outfall spillway bridge in place March 2008

 

 

 

There is also a project now under way for the last 3 years and due to be completed through summer 2008 to re-develop the whole terminus platform and station area to provide better catering and seating facilities and re roof the platform canopy as the old corrugated roofing is badly corroded at the edges. Architect plans were drawn and been passed by the council planning , and all materials are now on site. Foundation construction was completed in 2006 by local building contractor, and handed over to the FSMR team (led by  a member who is a skilled builder).

Currently in May, the roof has been slated and internal fitting commenced!

The new station building being based on the Midland Railways, Settle station design.

Follow the link to the new station page as this major project reaches its conclusion in 2008

 

station in Feb 2008 with roof joists being completed

 

Track

Ongoing re-sleepering of track continues, the original 1970's jarah sleepers showing their age, especially on the extension. Go to the picture gallery for pictures of the re-sleepering methods.

We have started the process of lifting complete panels and digging out the bed with the FSMR tractor loader. The bed then receives a geo-tex membrane before new ballast is added and the panel is  replaced on new sleepers. The record is 3 panels  completed in one day. The oldest sections are being tackled first through the woods. We are also took the opportunity this spring to install an access crossing at badgers curve to allow heavy machinery access without damage to the track  e.g tractor mower and JCB .At the same time, 9 panels of original track were renewed through the wooded section.

 

Another record in autumn 2006 with 4 panels !! replaced over the weekend of 14th 15th October 2006 in the same area back to badgers bend completing this area. We also added a new sleeper retaining walls to the bank to prevent soil erosion contamination of the ballast.

And all this with the Berkshire providing the exotic motive power for the day in the diesels absence

Follow this link for detailed pages and pictures of the October 2006 track work

 

 below is the work completed looking, towards badgers bend, on bonfire weekend with the Berkshire providing the works train motive power in the diesels absence

 

 

 

Yet another record in Feb 2008 with 6 panels !! being replaced over the Saturday 16th on Chestnuts curve

Follow this link for detailed pages and pictures of the Feb and March 2008 track work

 

We are also very grateful to Lafarge Aggregates at Mountsorrel, who supplied the SMR in 2005/2006 with a large tonnage of ballast to carry out track renewal

Check out their website for your aggregate and building supply needs

.

 See also the picture gallery for pictures of some more track work 

 

Locomotives

All locos are being prepared for the public operation weekends

"Warship" The Diesel suffered a failure of one of the bogie bearings in 2006 and was removed from service during the Autumn and winter for heavy overhaul. The bogies were removed and tripped down for rebuilding of the drive train. The fluid flywheel drive was put back after overhaul allowing the main drive to be completed. Other work was carried out at the same time, it was back in service by mid August 2007 and is now back on works train haulage duties.

 

 

 

Some FSMR members are also constructing their own 1/5th scale 10 1/4" gauge diesel or steam locos, these currently are:

 

Replica of 1899 Midland railway Johnson 4-2-2 "Spinner"

The tender is built, and work progresses on the rest, no arrival date at Stapleford yet!

 

Brush Class 60 D/E 

Fully working Diesel Electric replica featuring latest design in traction motors driven off a diesel alternator, just like the real thing!!

Date for arrival and commissioning 2008

 

 

 

  

BACK TO MAIN PAGE