Welcome to the Feb 2008 Trackwork  Page

of the FSMR website

 

These photos were taken during the  mid February track weekend in  2008 when 6 panels were lifted and replaced on chestnuts  curve on one Saturday breaking the previous record of 5 over two days,

 with the final ballasting completed on 8th March

 

The first task was to set up a laser level to maintain the gradient profile between the two untouched sections of line

This section was heavily contaminated with mud and clay and the sleepers were not visible and so a fully renewal of track bed was required following on form previous work carried out in the Autumn on the curve.

 

After cutting off the fishplate bolts and lifting the panels out onto the bank with the tractor, the next step is to use the tractor loader and hand tools!! to remove about 4 inches of the old track ballast (mostly mud!)

This is done in sections to allow the track to be re-laid behind the tractor as it continues to work forward

 

 

 

After the track-bed had been dug down to remove contaminated ground, the geotex membrane is added and newly sleepered track is put back. The track is then jacked up to correct height using the laser level datum points, ready for provisional  ballasting under the sleepers

 

 

The works train in front of the tractor is on the start of the original track which will be hopefully joined up with newly sleepered line

The fishplates are then fitted with new bolts and greased to ensure trouble free movement

 (critical to avoid thermal damage in the hot sun!!)

The packing depth under the sleepers can be seen from this shot

 

 

 

Three weeks later on a dry Saturday in March, and  the  ballasting to full depth is completed and track  aligned and then cross level checked before final tamping and further ballasting. Restraining spike posts are also hammered in on the outer radius edge of each main joint sleeper in order to maintain alignment under train cornering forces on the curves

The only remaining task is to build the single sleeper retaining wall and grade in the banks with the JCB

BACK TO PROJECTS PAGE

 

 

BACK TO MAIN PAGE