Welcome to the Oct 2006 Trackwork  page 2

of the FSMR website

 

These photos were taken during the  October track weekend in  2006 when 5 panels were lifted and replaced on badgers curve in one weekend. At the same time the opportunity was used to install a sleeper retaining wall against the earth bank at this location.

The works train in use over the weekend, having the luxury of steam power in the diesels absence on its heavy repair and overhaul this winter.

  

 

Two panels are already installed and ballasted. The tractor is completing compacting the loosened bed before the geo-tex is applied. The newly sleepered panel will then be connected onto the ballasted panel.

 The laser level ( setup at the beginning)  is used to maintain the gradient profile throughout the new length

 

 

After setting the track height using the laser, the track is then ballasted. There are two 2 ton ballast trucks on the SMR works train. One has end discharge (as shown here) the other has side discharge doors. The two run in pairs so that the whole section of track can be ballasted effectively.

Re-loading is carried out at the ballast tip by the station using the tractor loader

 

After being loaded with stone, the Berkshire heads off back to the work site with the works train.

Apart from the  two  4 axle ballast trucks, the works train usually consist of a flat truck for general conveying of sleepers etc ( also adapted to take the petrol driven 1000 l  weed-killing tank sprayer). There is also a 3 axle short wheelbase truck carrying fishplates, spikes and bolts shown ns shot.

 Also out of shot is the twin cylinder diesel 3 phase generator /  welding wagon. An essential piece of equipment on any track day.

 If there is a large number of personnel, a passenger coach is also added to the consist

 

 BACK TO PROJECTS

 

BACK TO THE GALLERY

 

BACK TO MAIN PAGE